Permits
Permit Guide
Every construction project in the Bahamas requires permits. Here is what you need, who issues them, how long they take, and what documents to prepare.
🏙 New Providence|⚓ Family Islands — see notes below each permit
permits
Planning Permission
Authority
Ministry of Works
Timeline
8–16 weeks
Required Documents
- · Site plan (surveyor-certified)
- · Architectural drawings
- · Title documents
- · Completed application form
- · Application fee
Required before any construction. Must be obtained first — building permit cannot be issued without it.
permits
Building Permit
Authority
Building Control Authority (BCA)
Timeline
4–8 weeks after planning
Required Documents
- · Planning permission approval
- · Structural drawings
- · Electrical drawings
- · Plumbing drawings
- · Contractor details
Fee is calculated per square foot of construction. Inspections required at foundation, frame, and completion stages.
permits
Environmental Permit
Authority
Bahamas Environment, Science & Technology (BEST) Commission
Timeline
12–24 weeks (EIA required)
Required Documents
- · Environmental Impact Assessment
- · Site plan
- · Project description
- · Mitigation plan
Required for large developments, coastal construction, and projects in environmentally sensitive areas.
permits
Subdivision Approval
Authority
Ministry of Works & Planning
Timeline
16–24 weeks
Required Documents
- · Survey plan
- · Title documents
- · Proposed lot layout
- · Infrastructure plan
Required when dividing land into multiple lots. Must show road access, utilities, and lot dimensions.
permits
BPL Connection
Authority
Bahamas Power & Light (BPL)
Timeline
4–12 weeks
Required Documents
- · Electrical inspection certificate
- · Building permit
- · Property ownership proof
- · BPL application form
Submit after electrical work is complete and inspected. Meter installation scheduled after approval.
permits
WSC Connection
Authority
Water & Sewerage Corporation (WSC)
Timeline
4–8 weeks
Required Documents
- · Plumbing inspection certificate
- · Building permit
- · Property ownership proof
- · WSC application form
Required for water and sewerage connections. Septic system approval separate if public sewerage unavailable.
Family Islands — Additional Requirements
- ⚓ Commissioner's approval required before planning permission on most Family Islands
- ⚓ Process and timelines vary significantly by island and Commissioner's office
- ⚓ Some islands have limited Ministry of Works presence — allow extra time
- ⚓ Environmental considerations more prominent on smaller, more fragile islands
- ⚓ Utility connections (BEC, WSC) may not be available — generator + cistern + septic common
Have specific questions about your project's permits?
Ask the Advisor