Step-by-Step: Getting Planning Permission in Nassau

Planning Permission from the Ministry of Works is the essential first step in any construction project in New Providence.
STEP 1: HIRE YOUR PROFESSIONAL TEAM
You will need a licensed Bahamian architect to prepare your drawings, and a registered surveyor to certify your site plan. Do not start drawings before confirming your land has clear title.
STEP 2: PREPARE YOUR DRAWINGS
Your architect must prepare:
- Site plan (showing property boundaries, setbacks, neighboring structures)
- Floor plans (all levels)
- Elevations (all four sides)
- Roof plan
- Sections
- Structural drawings (for anything beyond basic residential)
STEP 3: SUBMIT YOUR APPLICATION
Submit to the Department of Physical Planning at the Ministry of Works. Include:
- Completed application form
- 4 sets of drawings
- Site plan certified by registered surveyor
- Proof of land ownership (title documents or deed)
- Application fee (varies by project size)
STEP 4: AWAIT REVIEW
Typical review time: 8-16 weeks. The department may issue:
- Approval (with or without conditions)
- Request for more information
- Refusal (with grounds stated)
COMMON REASONS FOR REJECTION
- Insufficient setbacks from property lines
- Building height exceeds zone limits
- Lot coverage exceeds maximum allowed
- Inadequate parking provision
- Environmental concerns (coastal, wetland proximity)
STEP 5: AFTER PLANNING APPROVAL
With planning permission in hand, you can apply for your Building Permit from the Building Control Authority (BCA). Planning permission is valid for a limited period — begin construction before it expires.